Test rig program project plan template

A schedule for designing and building a test rig, with the two design reviews as gates. Long-lead parts are ordered after the preliminary review so the build can start soon after the critical review.

26 tasks29 weeks34 links
#TaskDurationStarts after
1Requirements
2Program kickoffMilestone
3Test requirements captured10 days2
4Rig specification agreed8 days3
5Requirements reviewMilestone4
6Preliminary design
7Concept layout and load paths15 days5
8Preliminary sizing and analysis10 days7 SS+5d
9PDR data pack5 days7, 8
10Preliminary design review (PDR)Milestone9
11Detail design
12Detail design and drawings30 days10
13Stress and fatigue analysis20 days10+5d
14Control and data system design20 days10
15CDR data pack5 days12, 13, 14
16Critical design review (CDR)Milestone15
17Long-lead parts
18Actuators and hydraulic power unit70 days10
19Bearings and couplings60 days10
20Load cells and instrumentation40 days14
21Manufacture
22Frame and fixtures fabricated30 days16
23Machined parts25 days16
24Control cabinet build20 days16
25Assembly
26Mechanical assembly15 days22, 23, 19
27Hydraulics installed and flushed8 days26, 18
28Instrumentation and wiring10 days26, 24, 20
29Commissioning
30Calibration of load and position5 days28, 27
31Shakedown runs8 days30
32Rig readiness reviewMilestone31
33Rig handed to the test teamMilestone32

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.