Templates · Aerospace

First article inspection project plan template

A schedule for bringing one new part number into production and proving it with a first article inspection, the way AS9102 lays it out. Material and tooling run in parallel, and special processes follow machining.

24 tasks16 weeks27 links
#TaskDurationStarts after
1Planning
2Purchase order and drawing receivedMilestone
3Drawing and specification review4 days2
4Balloon the drawing and list characteristics3 days3
5Process plan and routing5 days3
6Inspection plan and gauges4 days4
7Material and tooling
8Raw material with certificates25 days3
9Fixtures and cutting tools15 days5
10CNC programs8 days5
11Special gauges15 days6
12First run
13Machine setup and prove-out3 days8, 9, 10
14First production run5 days13
15In-process inspection2 days14
16Special processes
17Heat treat5 days15
18Non-destructive testing3 days17
19Surface finish and plating6 days18
20Part marking1 day19
21Inspection
22Full dimensional inspection4 days20, 11
23Collect material and process certificates3 days20
24First article inspection report (forms 1 to 3)3 days22, 23
25Internal quality review2 days24
26Approval
27Submit report to customerMilestone25
28Customer review10 days27
29First article approvedMilestone28
30Ship first lot2 days29

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.