Qualification test campaign project plan template
A schedule for qualifying one unit through a planned run of tests. The test readiness review is the gate: plan, procedures, fixtures and test articles all have to be there before the first test.
#TaskDurationStarts after
1Planning
2Campaign kickoffMilestone
3Qualification test plan15 days2
4Customer approval of test plan10 days3
5Test procedures15 days3
6Book test lab slots3 days3
7Preparation
8Fixture design and build25 days3
9Build test articles30 days2
10Instrumentation and data system set up5 days8, 9
11Baseline functional test3 days10, 5
12Test readiness review (TRR)Milestone11, 4, 6
13Dynamic tests
14Vibration5 days12
15Shock3 days14
16Functional check after dynamics2 days15
17Environmental tests
18Thermal cycling10 days16
19Humidity8 days18
20Altitude and pressure4 days19
21Functional check after environment2 days20
22Endurance
23Endurance run20 days21
24Final functional test2 days23
25Teardown inspection5 days24
26Report
27Data review5 days25
28Qualification test report10 days27
29Customer review of report10 days28
30Qualification signed offMilestone29
Red outline: the critical path, the tasks that set the finish date.
A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.
More aerospace plans
Test rig program
Requirements through PDR and CDR, long-lead parts, build, instrumentation and commissioning of a test rig.
Requirements
Preliminary design
Detail design
Long-lead parts
Manufacture
Assembly
Commissioning
First article inspection
A new part into production with a first article inspection report: planning, tooling, first run, inspection, approval.
Planning
Material and tooling
First run
Special processes
Inspection
Approval
Tooling and fixture build
Design, review, machining, assembly, inspection and buy-off for an assembly jig or test fixture.
Design
Procurement
Manufacture
Assembly
Inspection
Tryout