Templates · Aerospace
Tooling and fixture build project plan template
A schedule for one tool, such as an assembly jig, drill fixture or test fixture. The design review is the gate before metal is cut, and the tool is proven on a real part before buy-off.
#TaskDurationStarts after
1Design
2Tool order receivedMilestone
3Tool requirements and datum scheme4 days2
4Concept design8 days3
5Detail design and drawings12 days4
6Tool design reviewMilestone5
7Drawing updates from review3 days6
8Procurement
9Plate and stock material10 days6
10Bushings, clamps and bought-out parts15 days6
11Manufacture
12Machine base and frame12 days9, 7
13Machine locators and details15 days9, 7
14Heat treat and surface treatment5 days13
15Assembly
16Assemble and pin6 days12, 14, 10
17Set locators to nominal3 days16
18Tool identification and markings1 day17
19Inspection
20Dimensional inspection3 days17
21Inspection report2 days20
22Tryout
23First part tryout3 days21, 18
24Adjust and re-inspect3 days23
25Tool buy-offMilestone24
26Released to productionMilestone25
Red outline: the critical path, the tasks that set the finish date.
A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.
More aerospace plans
Test rig program
Requirements through PDR and CDR, long-lead parts, build, instrumentation and commissioning of a test rig.
Requirements
Preliminary design
Detail design
Long-lead parts
Manufacture
Assembly
Commissioning
Qualification test campaign
Test plan, fixtures, test readiness review, vibration, thermal and endurance tests, report and sign-off.
Planning
Preparation
Dynamic tests
Environmental tests
Endurance
Report
First article inspection
A new part into production with a first article inspection report: planning, tooling, first run, inspection, approval.
Planning
Material and tooling
First run
Special processes
Inspection
Approval