<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project"><SaveVersion>14</SaveVersion><Name>Test rig program</Name><ScheduleFromStart>1</ScheduleFromStart><StartDate>2027-01-04T08:00:00</StartDate><CalendarUID>1</CalendarUID><DefaultStartTime>08:00:00</DefaultStartTime><DefaultFinishTime>17:00:00</DefaultFinishTime><MinutesPerDay>480</MinutesPerDay><MinutesPerWeek>2400</MinutesPerWeek><DaysPerMonth>20</DaysPerMonth><Calendars><Calendar><UID>1</UID><Name>Test rig program</Name><IsBaseCalendar>1</IsBaseCalendar><BaseCalendarUID>-1</BaseCalendarUID><WeekDays><WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay><WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay></WeekDays><Exceptions></Exceptions></Calendar></Calendars><Tasks><Task><UID>1</UID><ID>1</ID><Name>Requirements</Name><WBS>1</WBS><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-01-04T08:00:00</Start><Finish>2027-01-28T17:00:00</Finish><Duration>PT152H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>2</UID><ID>2</ID><Name>Program kickoff</Name><WBS>1.1</WBS><OutlineNumber>1.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-04T17:00:00</Start><Finish>2027-01-04T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>3</UID><ID>3</ID><Name>Test requirements captured</Name><WBS>1.2</WBS><OutlineNumber>1.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-05T08:00:00</Start><Finish>2027-01-18T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>4</UID><ID>4</ID><Name>Rig specification agreed</Name><WBS>1.3</WBS><OutlineNumber>1.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-19T08:00:00</Start><Finish>2027-01-28T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>3</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>5</UID><ID>5</ID><Name>Requirements review</Name><WBS>1.4</WBS><OutlineNumber>1.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-28T17:00:00</Start><Finish>2027-01-28T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>6</UID><ID>6</ID><Name>Preliminary design</Name><WBS>2</WBS><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-01-29T08:00:00</Start><Finish>2027-02-25T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>7</UID><ID>7</ID><Name>Concept layout and load paths</Name><WBS>2.1</WBS><OutlineNumber>2.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-29T08:00:00</Start><Finish>2027-02-18T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>8</UID><ID>8</ID><Name>Preliminary sizing and analysis</Name><WBS>2.2</WBS><OutlineNumber>2.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-05T08:00:00</Start><Finish>2027-02-18T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>3</Type><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>9</UID><ID>9</ID><Name>PDR data pack</Name><WBS>2.3</WBS><OutlineNumber>2.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-02-25T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>8</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>10</UID><ID>10</ID><Name>Preliminary design review (PDR)</Name><WBS>2.4</WBS><OutlineNumber>2.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-25T17:00:00</Start><Finish>2027-02-25T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>11</UID><ID>11</ID><Name>Detail design</Name><WBS>3</WBS><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-04-15T17:00:00</Finish><Duration>PT280H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>12</UID><ID>12</ID><Name>Detail design and drawings</Name><WBS>3.1</WBS><OutlineNumber>3.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-04-08T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>13</UID><ID>13</ID><Name>Stress and fatigue analysis</Name><WBS>3.2</WBS><OutlineNumber>3.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-03-05T08:00:00</Start><Finish>2027-04-01T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>14</UID><ID>14</ID><Name>Control and data system design</Name><WBS>3.3</WBS><OutlineNumber>3.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-03-25T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>15</UID><ID>15</ID><Name>CDR data pack</Name><WBS>3.4</WBS><OutlineNumber>3.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-09T08:00:00</Start><Finish>2027-04-15T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>12</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>13</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>16</UID><ID>16</ID><Name>Critical design review (CDR)</Name><WBS>3.5</WBS><OutlineNumber>3.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-15T17:00:00</Start><Finish>2027-04-15T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>15</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>17</UID><ID>17</ID><Name>Long-lead parts</Name><WBS>4</WBS><OutlineNumber>4</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-06-03T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>18</UID><ID>18</ID><Name>Actuators and hydraulic power unit</Name><WBS>4.1</WBS><OutlineNumber>4.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-06-03T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>19</UID><ID>19</ID><Name>Bearings and couplings</Name><WBS>4.2</WBS><OutlineNumber>4.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-26T08:00:00</Start><Finish>2027-05-20T17:00:00</Finish><Duration>PT480H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>20</UID><ID>20</ID><Name>Load cells and instrumentation</Name><WBS>4.3</WBS><OutlineNumber>4.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-03-26T08:00:00</Start><Finish>2027-05-20T17:00:00</Finish><Duration>PT320H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>21</UID><ID>21</ID><Name>Manufacture</Name><WBS>5</WBS><OutlineNumber>5</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-04-16T08:00:00</Start><Finish>2027-05-27T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>22</UID><ID>22</ID><Name>Frame and fixtures fabricated</Name><WBS>5.1</WBS><OutlineNumber>5.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-16T08:00:00</Start><Finish>2027-05-27T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>23</UID><ID>23</ID><Name>Machined parts</Name><WBS>5.2</WBS><OutlineNumber>5.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-16T08:00:00</Start><Finish>2027-05-20T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>24</UID><ID>24</ID><Name>Control cabinet build</Name><WBS>5.3</WBS><OutlineNumber>5.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-16T08:00:00</Start><Finish>2027-05-13T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>25</UID><ID>25</ID><Name>Assembly</Name><WBS>6</WBS><OutlineNumber>6</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-05-28T08:00:00</Start><Finish>2027-07-01T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>26</UID><ID>26</ID><Name>Mechanical assembly</Name><WBS>6.1</WBS><OutlineNumber>6.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-05-28T08:00:00</Start><Finish>2027-06-17T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>22</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>27</UID><ID>27</ID><Name>Hydraulics installed and flushed</Name><WBS>6.2</WBS><OutlineNumber>6.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-18T08:00:00</Start><Finish>2027-06-29T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>28</UID><ID>28</ID><Name>Instrumentation and wiring</Name><WBS>6.3</WBS><OutlineNumber>6.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-18T08:00:00</Start><Finish>2027-07-01T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>29</UID><ID>29</ID><Name>Commissioning</Name><WBS>7</WBS><OutlineNumber>7</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-07-02T08:00:00</Start><Finish>2027-07-20T17:00:00</Finish><Duration>PT104H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>30</UID><ID>30</ID><Name>Calibration of load and position</Name><WBS>7.1</WBS><OutlineNumber>7.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-07-02T08:00:00</Start><Finish>2027-07-08T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>28</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>27</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>31</UID><ID>31</ID><Name>Shakedown runs</Name><WBS>7.2</WBS><OutlineNumber>7.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-07-09T08:00:00</Start><Finish>2027-07-20T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>30</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>32</UID><ID>32</ID><Name>Rig readiness review</Name><WBS>7.3</WBS><OutlineNumber>7.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-07-20T17:00:00</Start><Finish>2027-07-20T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>31</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>33</UID><ID>33</ID><Name>Rig handed to the test team</Name><WBS>7.4</WBS><OutlineNumber>7.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-07-20T17:00:00</Start><Finish>2027-07-20T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>32</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task></Tasks></Project>