Robotic cell integration project plan template

A schedule for integrating one robot cell, such as a palletizer or a machine-tending cell. The robot is ordered early because it sets the build date, and the risk assessment is closed before the customer run-off.

26 tasks25 weeks33 links
#TaskDurationStarts after
1Concept
2Kickoff and cycle time targetsMilestone
3Reach and cycle time simulation8 days2
4Cell layout and concept approval5 days3
5Risk assessment, first pass3 days4
6Design
7Mechanical design and guarding20 days4
8End-of-arm tooling design12 days4
9Controls design and safety circuit15 days5
10Design releaseMilestone7, 8, 9
11Purchased parts
12Robot and controller50 days4
13Safety scanners and light curtains20 days9
14Conveyors and pallet handling30 days10
15Build
16Base, risers and guarding fabricated15 days10
17End-of-arm tooling built12 days10
18Control panel build10 days10
19Set robot and assemble cell8 days16, 12, 14
20Field wiring and safety devices8 days19, 18, 13
21Program and run-off
22Robot programming12 days20, 17
23PLC and HMI programming15 days18
24Risk assessment closed and validated3 days22, 23
25Customer run-off at rate3 days24
26Run-off punch list5 days25
27Install
28Tear down, crate and ship5 days26
29Install and anchor on site5 days28+2d
30Commission with production parts8 days29
31Operator and maintenance training2 days30
32Customer acceptanceMilestone31

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.