PLC and HMI upgrade project plan template
A schedule for swapping an old PLC and operator screens on a line that has to keep running. Everything is proven on the bench first, so the cutover fits in one planned shutdown with a way back.
#TaskDurationStarts after
1Survey
2Kickoff on siteMilestone
3Site survey and panel photos3 days2
4I/O list and network map4 days3
5Functional description agreed5 days4
6Design
7Hardware design and adapter plan6 days4
8Updated electrical drawings6 days7
9Parts
10PLC, HMI and conversion kits25 days7
11Software
12Convert and clean up PLC code15 days5
13New HMI screens12 days5
14Alarms and recipes5 days13
15Bench test
16Bench setup with real hardware3 days10, 12
17Simulated run-through5 days16, 14
18Customer witness test2 days17
19Fixes from the witness test3 days18
20Cutover
21Cutover plan and way back agreed2 days18
22Pre-wire and pre-checks on site3 days19, 8
23Cutover during shutdown3 days22, 21
24I/O checkout and dry run2 days23
25Start-up with product2 days24
26Support
27On-site production support5 days25
28As-built drawings and backups3 days25
29Handover and closeMilestone27, 28
Red outline: the critical path, the tasks that set the finish date.
A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.
More automation and equipment plans
Build-to-order machine
Engineering, purchased parts, fabrication, assembly, FAT, ship and install for one custom machine.
Engineering
Purchased parts
Fabrication
Assembly
Factory acceptance
Ship and install
Robotic cell integration
Concept to production for a robot cell: simulation, guarding, end-of-arm tooling, risk assessment and run-off.
Concept
Design
Purchased parts
Build
Program and run-off
Install
Control panel build
Schematics, bill of material, enclosure layout, wiring, point-to-point checkout and power-up for one panel.
Design
Parts
Build
Checkout