<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project"><SaveVersion>14</SaveVersion><Name>Robotic cell integration</Name><ScheduleFromStart>1</ScheduleFromStart><StartDate>2027-01-04T08:00:00</StartDate><CalendarUID>1</CalendarUID><DefaultStartTime>08:00:00</DefaultStartTime><DefaultFinishTime>17:00:00</DefaultFinishTime><MinutesPerDay>480</MinutesPerDay><MinutesPerWeek>2400</MinutesPerWeek><DaysPerMonth>20</DaysPerMonth><Calendars><Calendar><UID>1</UID><Name>Robotic cell integration</Name><IsBaseCalendar>1</IsBaseCalendar><BaseCalendarUID>-1</BaseCalendarUID><WeekDays><WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay><WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay></WeekDays><Exceptions></Exceptions></Calendar></Calendars><Tasks><Task><UID>1</UID><ID>1</ID><Name>Concept</Name><WBS>1</WBS><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-01-04T08:00:00</Start><Finish>2027-01-26T17:00:00</Finish><Duration>PT136H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>2</UID><ID>2</ID><Name>Kickoff and cycle time targets</Name><WBS>1.1</WBS><OutlineNumber>1.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-04T17:00:00</Start><Finish>2027-01-04T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>3</UID><ID>3</ID><Name>Reach and cycle time simulation</Name><WBS>1.2</WBS><OutlineNumber>1.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-05T08:00:00</Start><Finish>2027-01-14T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>4</UID><ID>4</ID><Name>Cell layout and concept approval</Name><WBS>1.3</WBS><OutlineNumber>1.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-15T08:00:00</Start><Finish>2027-01-21T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>3</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>5</UID><ID>5</ID><Name>Risk assessment, first pass</Name><WBS>1.4</WBS><OutlineNumber>1.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-01-26T17:00:00</Finish><Duration>PT24H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>6</UID><ID>6</ID><Name>Design</Name><WBS>2</WBS><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-02-18T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>7</UID><ID>7</ID><Name>Mechanical design and guarding</Name><WBS>2.1</WBS><OutlineNumber>2.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-02-18T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>8</UID><ID>8</ID><Name>End-of-arm tooling design</Name><WBS>2.2</WBS><OutlineNumber>2.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-02-08T17:00:00</Finish><Duration>PT96H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>9</UID><ID>9</ID><Name>Controls design and safety circuit</Name><WBS>2.3</WBS><OutlineNumber>2.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-27T08:00:00</Start><Finish>2027-02-16T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>10</UID><ID>10</ID><Name>Design release</Name><WBS>2.4</WBS><OutlineNumber>2.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-18T17:00:00</Start><Finish>2027-02-18T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>8</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>11</UID><ID>11</ID><Name>Purchased parts</Name><WBS>3</WBS><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-04-01T17:00:00</Finish><Duration>PT400H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>12</UID><ID>12</ID><Name>Robot and controller</Name><WBS>3.1</WBS><OutlineNumber>3.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-01-22T08:00:00</Start><Finish>2027-04-01T17:00:00</Finish><Duration>PT400H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>13</UID><ID>13</ID><Name>Safety scanners and light curtains</Name><WBS>3.2</WBS><OutlineNumber>3.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-17T08:00:00</Start><Finish>2027-03-16T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>14</UID><ID>14</ID><Name>Conveyors and pallet handling</Name><WBS>3.3</WBS><OutlineNumber>3.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-04-01T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>15</UID><ID>15</ID><Name>Build</Name><WBS>4</WBS><OutlineNumber>4</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-04-23T17:00:00</Finish><Duration>PT368H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>16</UID><ID>16</ID><Name>Base, risers and guarding fabricated</Name><WBS>4.1</WBS><OutlineNumber>4.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-03-11T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>17</UID><ID>17</ID><Name>End-of-arm tooling built</Name><WBS>4.2</WBS><OutlineNumber>4.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-03-08T17:00:00</Finish><Duration>PT96H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>18</UID><ID>18</ID><Name>Control panel build</Name><WBS>4.3</WBS><OutlineNumber>4.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-02-19T08:00:00</Start><Finish>2027-03-04T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>19</UID><ID>19</ID><Name>Set robot and assemble cell</Name><WBS>4.4</WBS><OutlineNumber>4.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-02T08:00:00</Start><Finish>2027-04-13T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>12</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>20</UID><ID>20</ID><Name>Field wiring and safety devices</Name><WBS>4.5</WBS><OutlineNumber>4.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-14T08:00:00</Start><Finish>2027-04-23T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>13</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>21</UID><ID>21</ID><Name>Program and run-off</Name><WBS>5</WBS><OutlineNumber>5</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-03-05T08:00:00</Start><Finish>2027-05-26T17:00:00</Finish><Duration>PT472H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>22</UID><ID>22</ID><Name>Robot programming</Name><WBS>5.1</WBS><OutlineNumber>5.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-04-26T08:00:00</Start><Finish>2027-05-11T17:00:00</Finish><Duration>PT96H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>17</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>23</UID><ID>23</ID><Name>PLC and HMI programming</Name><WBS>5.2</WBS><OutlineNumber>5.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-03-05T08:00:00</Start><Finish>2027-03-25T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>24</UID><ID>24</ID><Name>Risk assessment closed and validated</Name><WBS>5.3</WBS><OutlineNumber>5.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-05-12T08:00:00</Start><Finish>2027-05-14T17:00:00</Finish><Duration>PT24H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>22</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>25</UID><ID>25</ID><Name>Customer run-off at rate</Name><WBS>5.4</WBS><OutlineNumber>5.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-05-17T08:00:00</Start><Finish>2027-05-19T17:00:00</Finish><Duration>PT24H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>26</UID><ID>26</ID><Name>Run-off punch list</Name><WBS>5.5</WBS><OutlineNumber>5.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-05-20T08:00:00</Start><Finish>2027-05-26T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>25</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>27</UID><ID>27</ID><Name>Install</Name><WBS>6</WBS><OutlineNumber>6</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2027-05-27T08:00:00</Start><Finish>2027-06-25T17:00:00</Finish><Duration>PT176H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>1</Summary><PercentComplete>0</PercentComplete></Task><Task><UID>28</UID><ID>28</ID><Name>Tear down, crate and ship</Name><WBS>6.1</WBS><OutlineNumber>6.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-05-27T08:00:00</Start><Finish>2027-06-02T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>29</UID><ID>29</ID><Name>Install and anchor on site</Name><WBS>6.2</WBS><OutlineNumber>6.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-07T08:00:00</Start><Finish>2027-06-11T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>28</PredecessorUID><Type>1</Type><LinkLag>9600</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>30</UID><ID>30</ID><Name>Commission with production parts</Name><WBS>6.3</WBS><OutlineNumber>6.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-14T08:00:00</Start><Finish>2027-06-23T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>29</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>31</UID><ID>31</ID><Name>Operator and maintenance training</Name><WBS>6.4</WBS><OutlineNumber>6.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-24T08:00:00</Start><Finish>2027-06-25T17:00:00</Finish><Duration>PT16H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>30</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task><Task><UID>32</UID><ID>32</ID><Name>Customer acceptance</Name><WBS>6.5</WBS><OutlineNumber>6.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2027-06-25T17:00:00</Start><Finish>2027-06-25T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><PercentComplete>0</PercentComplete><PredecessorLink><PredecessorUID>31</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task></Tasks></Project>