Templates · Automation and equipment

Build-to-order machine project plan template

A schedule for one machine built to a customer’s order, from kickoff to production handover. Purchased parts run beside fabrication, and the factory acceptance test waits for both.

22 tasks26 weeks26 links
#TaskDurationStarts after
1Engineering
2Order kickoff with customerMilestone
3Layout and footprint approval5 days2
4Mechanical design20 days3
5Electrical schematics12 days4+5d
6Engineering release to shopMilestone4, 5
7Purchased parts
8Servo drives and motors30 days3
9Infeed conveyor25 days6
10Guarding and polycarbonate15 days6
11Fabrication
12Frame weldment10 days6
13Powder coat frame5 days12
14Machined parts15 days6
15Assembly
16Mechanical assembly15 days13, 14, 9
17Control panel build10 days8
18Field wiring8 days16, 17
19Debug and dry cycle10 days18, 10
20Factory acceptance
21Factory acceptance test (FAT)3 days19
22FAT punch list5 days21
23Ship and install
24Split, crate and ship5 days22
25Install and level on site5 days24+3d
26Site acceptance test (SAT)3 days25
27Operator training2 days26
28Production handoverMilestone27

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.