Templates · Automation and equipment

Control panel build project plan template

A short schedule for one industrial control panel, from approved schematics to a crated panel. Parts are ordered as soon as the bill of material is released, and wiring starts when the backplane is laid out.

17 tasks10 weeks21 links
#TaskDurationStarts after
1Design
2Order receivedMilestone
3Electrical schematics8 days2
4Bill of material2 days3
5Customer approval of drawings5 days3
6Release to buildMilestone4, 5
7Parts
8Enclosure and backplane10 days4
9PLC, drives and components20 days4
10Wire labels and nameplates3 days6
11Build
12Backplane layout, drill and tap3 days8, 6
13Mount duct, rail and components3 days12, 9
14Wire the panel8 days13, 10
15Door devices and harness2 days13
16Checkout
17Point-to-point check2 days14, 15
18Power-up and I/O check2 days17
19As-built drawings and label1 day18
20Crate and ship1 day19
21Panel shippedMilestone20

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.