Control panel build project plan template
A short schedule for one industrial control panel, from approved schematics to a crated panel. Parts are ordered as soon as the bill of material is released, and wiring starts when the backplane is laid out.
#TaskDurationStarts after
1Design
2Order receivedMilestone
3Electrical schematics8 days2
4Bill of material2 days3
5Customer approval of drawings5 days3
6Release to buildMilestone4, 5
7Parts
8Enclosure and backplane10 days4
9PLC, drives and components20 days4
10Wire labels and nameplates3 days6
11Build
12Backplane layout, drill and tap3 days8, 6
13Mount duct, rail and components3 days12, 9
14Wire the panel8 days13, 10
15Door devices and harness2 days13
16Checkout
17Point-to-point check2 days14, 15
18Power-up and I/O check2 days17
19As-built drawings and label1 day18
20Crate and ship1 day19
21Panel shippedMilestone20
Red outline: the critical path, the tasks that set the finish date.
A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.
More automation and equipment plans
Build-to-order machine
Engineering, purchased parts, fabrication, assembly, FAT, ship and install for one custom machine.
Engineering
Purchased parts
Fabrication
Assembly
Factory acceptance
Ship and install
Robotic cell integration
Concept to production for a robot cell: simulation, guarding, end-of-arm tooling, risk assessment and run-off.
Concept
Design
Purchased parts
Build
Program and run-off
Install
PLC and HMI upgrade
Replace an obsolete controller on a running line: code conversion, bench test, cutover weekend and support.
Survey
Design
Parts
Software
Bench test
Cutover
Support