Templates · Aerospace
Supplier source transfer project plan template
A schedule for moving a part from one supplier to another without missing a delivery. Safety stock is built at the old source while the new one works through tooling, first articles and a qualification lot.
#TaskDurationStarts after
1Selection
2Transfer approved to startMilestone
3Shortlist and request quotes10 days2
4Supplier audit5 days3
5Award and contract10 days4
6Customer notified of source change3 days5
7Bridge stock
8Safety stock plan agreed5 days2
9Old source builds safety stock60 days8
10Data and tooling
11Data package handed over5 days5
12Tooling moved or made30 days11
13Material ordered by new source30 days11
14New source process planning15 days11
15First articles
16First article run10 days12, 13, 14
17Special processes8 days16
18First article inspection5 days17
19First article approved5 days18
20Qualification lot
21Qualification lot built20 days19
22Lot inspection and test5 days21
23Fit check at assembly3 days22
24New source qualifiedMilestone23, 6
25Ramp
26First rate deliveries20 days24
27Deliveries at full rate20 days26
28Old source closed out5 days27, 9
29Transfer completeMilestone28
Red outline: the critical path, the tasks that set the finish date.
A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.
More aerospace plans
Test rig program
Requirements through PDR and CDR, long-lead parts, build, instrumentation and commissioning of a test rig.
Requirements
Preliminary design
Detail design
Long-lead parts
Manufacture
Assembly
Commissioning
Qualification test campaign
Test plan, fixtures, test readiness review, vibration, thermal and endurance tests, report and sign-off.
Planning
Preparation
Dynamic tests
Environmental tests
Endurance
Report
First article inspection
A new part into production with a first article inspection report: planning, tooling, first run, inspection, approval.
Planning
Material and tooling
First run
Special processes
Inspection
Approval