Templates · Aerospace

Ground support equipment project plan template

A schedule for one piece of ground support equipment, such as an engine stand, lifting sling or transport fixture. The stress check is finished before release, and the proof load test is the gate before delivery.

21 tasks17 weeks23 links
#TaskDurationStarts after
1Requirements
2Order receivedMilestone
3Requirements and interfaces5 days2
4Concept and customer agreement8 days3
5Design
6Detail design15 days4
7Stress check and safety factors8 days6 SS+5d
8Design reviewMilestone6, 7
9Released drawings3 days8
10Procurement
11Structural steel and plate12 days8
12Rated hardware and casters20 days8
13Fabrication
14Cut and prepare5 days11, 9
15Weld10 days14
16Weld inspection3 days15
17Machine interfaces5 days16
18Finish and assembly
19Blast and paint5 days17
20Assemble with hardware4 days19, 12
21Load placards and identification1 day20
22Test and delivery
23Proof load test2 days21
24Inspection after proof load2 days23
25Certificate and user instructions3 days24
26Pack and deliver3 days25
27Accepted by customerMilestone26

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.