Templates · Automation and equipment

Conveyor line install project plan template

A schedule for installing a conveyor line on a customer’s site. It starts with what the site must have ready, then runs mechanical and electrical work in overlap and ends with a rate test.

23 tasks13 weeks27 links
#TaskDurationStarts after
1Site readiness
2Site kickoff and safety orientationMilestone
3Floor survey and layout marking3 days2
4Power and air drops by the site10 days2
5Area cleared and releasedMilestone3, 4
6Delivery
7Deliver and unload2 days5
8Stage and check against packing list2 days7
9Mechanical install
10Set and anchor supports5 days8
11Install conveyor beds and drives8 days10
12Transfers, merges and guards5 days11
13Level and align3 days12
14Electrical install
15Cable tray and conduit6 days10
16Pull and terminate cable8 days15, 11
17Set and land control panels3 days15
18Checkout
19I/O checkout4 days16, 17
20Motor rotation and bump test2 days19, 13
21Emergency stop and safety check2 days20
22Commissioning
23Dry run without product3 days21
24Run with product and tune5 days23
25Rate test2 days24
26Acceptance
27Site acceptance test (SAT)2 days25
28Operator and maintenance training2 days27
29Punch list5 days27
30Handover to productionMilestone28, 29

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.