Capital equipment purchase project plan template

A schedule for buying a machine, written from the buyer’s chair. It covers the months before the purchase order as well as the supplier’s build, with the approvals and site work you owe the supplier along the way.

24 tasks32 weeks28 links
#TaskDurationStarts after
1Requirements
2Project approved to startMilestone
3User requirements written10 days2
4Budget estimate and justification8 days3
5Funding approved10 days4
6Supplier choice
7Request for quotes sent3 days3
8Suppliers prepare quotes15 days7
9Compare quotes and visit suppliers8 days8
10Purchase order placedMilestone9, 5
11Design approvals
12Layout approval10 days10
13Design review with supplier3 days12+15d
14Send sample parts to supplier5 days10
15Supplier build
16Supplier builds the machine70 days12
17Progress visit1 day16 SS+40d
18Site preparation
19Utilities and foundations25 days12
20Permits and safety review15 days12
21Floor space cleared5 days19
22Acceptance and delivery
23Factory acceptance test at supplier3 days16, 14
24Supplier closes FAT items8 days23
25Shipping8 days24
26Install and qualify
27Install and connect8 days25, 21, 20
28Site acceptance test3 days27
29Training3 days28
30Process qualification runs10 days28
31Released to productionMilestone30, 29

Red outline: the critical path, the tasks that set the finish date.

A made-up example with typical durations in working days, Monday to Friday. Change them to match your shop.